Colony Status — Under Development, Sector 88A

Building IND RAS — 77 plots, one association, complete transparency.

The official resident body for plot owners of IND RAS, Sector 88A, Gurugram. Track your property records, follow committee decisions, and see exactly where colony infrastructure stands.

0
Total Plots
0/77
Owners Registered
0%
Infrastructure Complete
0
Active Action Items
About the Association

Formed by owners, for owners.

IND RAS Plot Owners Association was formed by residents of Sector 88A to represent buyer interests directly with the developer and DTCP/HSVP while the colony is being built out — keeping records straight and follow-ups on the record.

Transparency

Every plot's registration, construction and document status is visible to all 77 owners — no closed-door decisions.

Documentation

Layout approvals, RERA registration and legal templates are held centrally so owners never chase paperwork alone.

Accountability

Every meeting point is logged with the action taken and its status, so nothing raised by an owner gets forgotten.

Plot Directory

All 77 plots, at a glance.

Hover a plot to see its build status. This reflects individual construction progress on each owner's plot — separate from the colony-wide infrastructure tracked below.

Construction complete
Under construction
Not started
Documents pending
Plot No.OwnerSizeFacingConstructionDocuments
B-07Rajesh Malhotra250 sq. yd.EastCompleteVerified
B-14Vikram Chauhan300 sq. yd.NorthUnder constructionVerified
B-23Priya Nanda200 sq. yd.SouthNot startedVerified
B-32Neha Sabharwal250 sq. yd.EastCompleteVerified
B-45Simran Kaur300 sq. yd.WestUnder constructionPending
B-61Anil Yadav200 sq. yd.NorthNot startedVerified
Documents

Layout approvals & legal records.

Colony-wide approvals held by the association, plus the standard templates every owner's individual plot file is checked against.

DTCP Approved Layout Plan

License No. LC-2114/2022

HRERA Registration Certificate

HRERA-GGM-0442-2022

Conveyance Deed — Template

Standard format, all plots

Allotment Letter — Template

Issued per plot at booking

Fire & Pollution NOC

Colony-wide clearance

Payment & Possession Schedule

Installment plan, all plots
Managing Committee

Who's running the association.

Office bearers elected by plot owners for the current term, each also a resident owner within the colony.

VC

Vikram Chauhan

President
Plot B-14President since 2024
NS

Neha Sabharwal

Secretary
Plot B-32Handles correspondence
RM

Rajesh Malhotra

Treasurer
Plot B-07Maintains corpus fund
SK

Simran Kaur

Joint Secretary
Plot B-45Documentation lead
AY

Anil Yadav

Executive Member
Plot B-61Site & security
PN

Priya Nanda

Executive Member
Plot B-23Community liaison
Meetings & Action Taken

Every point raised, every action logged.

A running record of committee and general body meetings — what was discussed, what the committee did about it, and where it stands today.

15 June 2026
General Body Meeting
In Progress

Points Discussed

  • Sewage line not yet connected to Sector 88A main line
  • Street lighting non-functional on Roads 3 & 5
  • Boundary wall along the eastern side incomplete

Action Taken

  • Written notice sent to developer with 30-day deadline
  • Complaint escalated to DTCP Enforcement Wing
  • Site visit conducted with the electrical contractor
18 May 2026
Managing Committee Meeting
Resolved

Points Discussed

  • Water tanker contract renewal for summer months
  • Security guard rotation at the main entry gate
  • Illegal debris dumping near Plots B-60 to B-65

Action Taken

  • New tanker vendor finalised — Shree Ganesh Water Supply
  • Guard roster revised to cover night shift gaps
  • Barricade installed at the dumping site
22 April 2026
General Body Meeting
Resolved

Points Discussed

  • Formal registration status of the association
  • Collection of one-time maintenance corpus fund
  • Priority sequence for internal road tarring

Action Taken

  • Registered under the Haryana Registration & Regulation of Societies Act
  • Corpus fund collection opened, per-plot contribution fixed
  • Road tarring tender floated to three contractors
Colony Progress

Shared infrastructure, tracked openly.

Overall development of Sector 88A's common infrastructure, as built out by the developer and monitored by the association.

0%
Overall

Infrastructure is 66% complete colony-wide.

Boundary security and internal roads are furthest along; the parks and green belt are next in the developer's sequence, with the association pressing for sewage and water-line completion this quarter.

Internal Roads85%
Sewage & Drainage Network60%
Electricity & Street Lighting70%
Boundary Wall & Main Gate Security95%
Water Supply Line55%
Parks & Green Belt30%